Applus+ around the world
Close Countries Panel
  • GLOBAL SITE
  • Belgium
  • Brazil
  • China
  • Czech Republic
  • France
  • Germany
  • India
  • Indonesia
  • Italy
  • Japan
  • Malaysia
  • México
  • Poland
  • Russia
  • Slovakia
  • South Africa
  • South Korea
  • Spain
  • Sweden
  • Taiwan
  • Thailand
  • Turkey
  • UK
  • United Kingdom
  • USA
Close Divisions Panel
Applus+ DIVISIONS
Energy & Industry Division
Industrial and environmental inspection, vendor inspection, technical assistance, non-destructive testing (NDT) and technical staffing for all type of industries.
Logo RTD Logo VELOSI Logo NORCONTROL Logo Intec Logo K2
Logo Ingelog Logo JAN Logo Kiefer Logo Novotec Logo NRay
Logo PTJava Logo Skc Logo XRay Logo Qualitec
Laboratories Division
Multidisciplinary laboratories.Testing and engineering for product development. Conformity testing and product certification. SYSTEMS CERTIFICATION.
Logo Applus Laboratories Logo Applus Certification
Automotive Division
Statutory vehicle inspection services and emission & gas testing solutions worldwide.
Logo Applus Automotive Logo Applus ITVE Logo NCT Logo Applus Bilsyn Logo K1
Logo Technologies Logo ITVs Logo Riteve
IDIADA Division
Design, engineering, testing and homologation services for the automotive industry worldwide.
Logo Applus IDIADA
News

Qatar CIPP Lining Team

10/06/2019
Applus+ Velosi specializes in trenchless techniques for the rehabilitation of drains and pipelines.
No-Dig or Trenchless Technology is the discipline of installing, repairing or renewing underground pipes, ducts, and cables using techniques that minimise or eliminate the need for excavation. 
 
Cured-in-place pipe (CIPP) is one of several trenchless rehabilitation methods used by Applus+ Velosi to repair existing pipelines. CIPP is a jointless, seamless, pipe-within-a-pipe with the capability to rehabilitate pipes ranging in diameter from DN 100 to DN 1600. The process is carried out through the manholes, avoiding excavation and traffic congestion.
 
There are several different materials and methods of curing, Applus+ Velosi are lining with glass reinforced liners which are cured using UV technology. The majority of pipes being rehabilitated using CIPP are sewer and drainage; these lines will have internal failings and infiltration problems. Once lined these pipes will be good for another 50 years.
 
Recently, Applus+ Velosi in Qatar’s CIPP lining team installed a 59m 800mm diameter CIPP GRP liner at a project site in Doha, this is the first of its kind in Qatar, and we are extremely happy with the installation.
During the installation, there were many challenges, the main one being the amount of infiltration coming from a 45m longitudinal fracture at the invert of the pipe. Applus+ Velosi and their client came up with an innovative solution to de-water next to the pipeline and lower the water table; this enabled us to install the liner in dry working conditions. 
 